This contract provides for water service extensions to residential customers and extensions to customers experiencing health risks associated with well water per a City Council approved policy. The purpose of the program is to provide service to new customers.
Long Creek Wastewater Treatment Plant – Cancelled
This project provides for up to 11 million gallons per day (MGD) of capacity at a proposed treatment plant at Long Creek, near the Long Creek pump station.
Belmont Lift Station and Forcemain
Design and construction of a Lift Station and Forcemain to transfer wastewater flows from Belmont to the Charlotte Water sanitary sewer collection system.
Beaver Dam Creek West Branch Outfall- Cancelled
This project consists of the design and construction of a sanitary sewer outfall along Beaver Dam Creek West Branch.
Beaverdam Creek Lift Station Improvements New Pump Stations – CANCELLED
This project will provide the necessary upgrades needed to support the proposed development called the River District.
Old Dowd Rd Airport 24-inch Water Main – Cancelled
The project is approximately 3600 linear feet of 24 inch water main connecting the existing line at Old Down Road to the 24 inch line on the east side of the airport.
Six Mile Creek PS Improvements-Cancelled
The purpose of this project is to eliminate the long shafts between the pumps and motors. Custom motor stands will be built to position the motors over the pumps. The original two motors for this pump station will also be replaced.
Taggart Creek Outfall Flow Diversion Structure-Cancelled
Project consists of the design and construction of a flow diversion structure.
Upper Taggart Creek Outfall Replacement
Project includes the construction of approximately 10,200 linear feet of 36, 30, 24, and 18 inch gravity sewer to address capacity concerns in the Upper Taggart Creek Outfall.