This solicitation will be used for addressing the physical barriers identified in the city’s ADA Transition Plan. Areas include but are not limited to; restrooms, water fountains, signage, handrails/guardrails, doors & hardware, main lobby service area, exterior sidewalks, parking, and striping.
Basement Condenser Water Loop Extension
This project includes the extension of the existing basement refrigeration condenser water loop. The awarded contractor shall be responsible for the installation of a 2” refrigeration condenser water loop main extension from the basement level of the main terminal to a tie-in point on the ramp level baggage handling room. The awarded contractor shall be responsible for coordinating condenser water pipe routing with the Terminal Lobby Expansion contractor prior to construction. In addition, the awarded contractor shall coordinate existing condenser water system shutdown(s) as needed to complete the system tie-in.
Firehouse #30 Replacement
Firehouse #30, currently located at 4707 Belle-Oaks Drive, near Charlotte Douglas Airport, is currently located in a house built in 1955 and needs extensive renovations. The facility is the only firehouse where crews must leave their living quarters to access their apparatus, as a result, in impacting response time.
Firehouse #30 design services with the use of Advance Planning funds will be utilized to build a replacement 3-bay 2-story firehouse to manage response volumes in the Beam Road/Airport area. The new facility will be approximately 14,000 square feet. The building will be located at 3019 Beam Road, directly across from the Police and Fire Academy, and the parcel ID number is 141-24-104. It is located in Council District 3. The firehouse design will be the same floor plan design as Hidden Valley Firehouse #45 (HVFH#45). This project is also designated to be an all-electric firehouse and additional scope will be added.
Franklin Water Treatment Plant Clearwell Improvements
Charlotte Water is requesting bids for construction of the Franklin Water Treatment Plant Clearwell project. This project includes installation of large diameter (72 to 120 inch) pipes, valves, and fittings. It also includes constructing a new chemical feed system, including a new building, pumps, storage silos, and chemical piping.
CLT – HVAC Maintenance Services – CANCELLED
The Facilities Department of Charlotte Douglas International Airport maintains a portfolio of various buildings, including the airport terminal, offices, fire stations, and tenant buildings, among others. The intent of this solicitation is to have a Company provide HVAC services for various Airport properties. The scope of services is required to assist the Airport with renovations, remodels, and maintenance of existing facilities. It will also include, but not limited to the following: service work, refrigerant, and hydronic piping, installation of equipment, duct work, insulation, and low voltage wiring.
Three (3) year term with two (2) additional one (1) year renewals.
CLT – Air Filter Services – DUPLICATE (VOID)
Provide air filtration products and perform quarterly changes of these air filtration products for the air handling units which condition the air for the main terminal building, five concourses, and the CLT Center. Provide the labor to install the new air filters and to dispose of the old air filters from each of the air handling units in the service areas.
Three (3) year term with two (2) additional one (1) year renewals.
McAlpine Wastewater Treatment Plant Dewatering Building HVAC Replacement
Replacing the McAlpine Waste Water Treatment Plant Dewatering Building HVAC system including all associated mechanical equipment, electrical, I&C, and ancillary components.
This project includes the HVAC upgrades at McAlpine Creek WWTP Thickening/Dewatering Building. The upgrades would include the replacement of air handling units, make up air units, exhaust fans, ductworks, the addition of split AC units, and the addition of an alarm and monitoring system for HVAC equipment. The scope will also include some structural and architectural rehabilitation needed to accommodate new ductwork and HVAC equipment.
Concourse E – Hot Water Piping Relocation
This project is to relocate the heating hot water piping from under the ramp pavement and concourse floor and reconnect in the terminal ceiling space. 60% night work, 40% daytime work. Project term will be 150 days.
Fire Station #35 HVAC Renovation (Re-bid)
This project will renovate the existing HVAC System, Controls and Water heaters for Charlotte Fire Station 35. The scope of work includes removal and disposal of the existing mechanical system ductwork, furnaces, condensers, and dedicated outdoor air unit and installation of new mechanical split system
Dx/Furnaces and air distribution, and reconnect with existing DDC controls.