Replacement of diffuser discs in aeration basins 3 and 4. Structural repairs in basins. Baffle installation and mixer rehabilitation.
Stowe Regional Water Resource Recovery Facility Southern Access Roads
The Project is for the construction of an extension of the existing access road at the Long Creek Pump Station for operational connectivity between the proposed Stowe Regional Water Resource Recovery Facility (WRRF) and Long Creek Pump Station (Southern Access Road). The Southern Access Road consists of approximately 650 linear feet of paved roadway with 2-12 feet travel lanes and a three span approximately 235 feet long bridge that accommodates the two travel lanes and a pedestrian/utility corridor lane over Long Creek.
McAlpine Low Lift Pump Station Improvements
This project consists of the replacement of low lift station pump check valves. The project will also include filter improvements and non-potable water upgrades, electrical updates, and a sluice gate replacement.
FY22 New Construction Services Miscellaneous Contract #1
This solicitation will provide for ongoing construction services for the installation of large water and sewer services as requested for commercial/residential use. The work also includes opportunities for installation of short street main extensions (< 100′), fire hydrant relocations and dismantlements as related to new requests.
FY22 New Services Miscellaneous Contract #2 – CANCELLED
Ongoing contract for installation of large water and sewer services as requested for commercial/residential use. Also includes opportunities for short street main extensions (< 100′), fire hydrant relocations and dismantlements as related to new requests
Sugar Creek 78” Sanitary Sewer Rehabilitation Project
The Project consists of rehabilitation of approximately 2,700 feet of 78-inch sanitary sewer via cured-in-place pipe lining (CIPP) including all preparatory work such as sewer cleaning nd television inspection, bypass pumping of wastewater flows, and complete restoration.
Site Improvements at Charlotte Water’s Field Operations, Zone 1 & 2
The Project consists of the repaving of two different Charlotte Water Facilities: Zone 1 which is located at 11609 Hord Drive Huntersville, NC 28078, and Zone 2 located at 5730 General Commerce Drive Charlotte, NC 28213. Zone 1 encompasses additional aspects besides the repaving, including a proposed storm drainage system, water and sanitary sewer extensions, and the enlargement of the existing detention pond. Zone 2 includes some storm drainage, curb and gutter, and concrete apart from the repaving.
McAlpine Large Diameter Sewer Rehabilitation – Phase 2
This project involves the rehabilitation of approximately 7,000 linear feet of reinforced concrete pipe (RCP) sewer outfall. The sewer outfall is located just south of Highway 51, running parallel to McAlpine Creek. The work will improve the structural integrity and performance of the sewer system.