The following specification is for work on 2 crossings Sweden and Hebron Rd. CATS is looking to stabilize and level crossing tub panels that are pumping. This will involve 5 outbound panels at Sweden and 4 inbound panels at Hebron. CATS will require the contractor to pump a polyurethane stabilization foam that is specifically designed to fill under the crossing structures without causing lift by filling the void that was created from these tubs pumping.
Each crossing on the Blue Line has a soil consist of solid particles and the spaces (voids) between these particles. However, void spaces in soil has caused big problems for these road crossings. Under concentrated loads, crossing tubs can literally squeeze air and water from soil as traffic transverse over it. When this happens, the soil sinks and crossing tubs follow closely behind and begin to pump creating defects and damaging the tubs.
The contractor will simply drill strategically placed holes into each panel. Using a portable pump and flexible hoses, they will fill these holes with the mixture (polyurethane foam) Lifting the panel crossing using this method. The contractor will perform this work during a weekend or beginning at non-revenue hours. CATS requires the contractor to provide a work schedule that will show a timetable of beginning work to completion for both Sweden and Hebron Rd. Crossings.
829
This project is to install a new chlorine dioxide line from the Dukes Water Treatment Plant to the intake. The scope also includes the replacement of the existing chemical piping.
The proposed Zone 4 project will include a 36,000 sf operations center, approximately 20,000 sf of pre-engineered metal structures to house open storage, crew storage, raw materials bunkers, two (2) combination trucks, fabrication shop, and two (2) fleet maintenance bays. The project will also include demolition of existing facilities in a phased approach so as to minimally impact or impede current operations on the site. The project may also include roadway improvements to West Tyvola Road to increase accessibility to the site.
Rodgers Builders was selected as the Construction Manager at Risk (CMAR) for this project.
This project will install new concrete and asphalt pavement improvements at the Fleet Management Sweden Road shop.
This project will construct sidewalk along the south side of Pleasant Grove Road from Hipp Road to Oakdale Elementary School. This project has been cancelled.
Construction of a roundabout at the Shade Valley Road/ Oakhurst Commons Drive intersection and installing a 10 to 12 ft. concrete multi-use path along Monroe Road. Amenities include: sidewalk curb & gutter, planting strips, accessible ramps truck apron, pedestrian refuge islands, and a sand filter stormwater detention pond.
This project will install sidewalk along the west side of Sharon Road from Bramwyck Drive to Chandworth Road.
This project will incorporate pedestrian, bicycle and bridge improvements on Matheson Avenue from North Tryon Street to Jordan Place. The project will include a westbound one-way bicycle path along the north side of Matheson Avenue and a two- way bicycle path and sidewalk along the south side. Both sides will include a three-foot buffer between the bicycle paths and the road.
This project is the second phase of 16th Street Streetscape project. Streetscape improvements include concrete sidewalk and ramps, curb and gutter, storm drainage, erosion control, slope grading work, and installation of a soil nail retaining wall on 16th Street adjacent to the Norfolk Southern parcel, at the northeast corner of N. Tryon Street and 16th Street intersection.