Vest Water Treatment Plant to Franklin Water Treatment Plant Force Main and Lee Duke Water Treatment Plant Chem Feed Improvements

 The Project consists of two scopes of work.

Scope 1: Vest Water Treatment Plant to Franklin Water Treatment Plant Force Main consists of installing over 16,000 linear feet of 16” ductile iron piping force main for residual and backwash transfer between the Vest Water Treatment Plant and the Franklin Water Treatment Plant. Installation of all associated fittings, valves, air release valves, trenching, trenchless crossings, parallel future piping, paving, connections, corrosion control, erosion control, cleaning, testing, and all other associated pipeline work. Installation of two crossings at CSX railroad and NCDOT I-85 Interstate, consisting of parallel 16” ductile iron carrier pipe inside single casing. Reporting on material of service connections along alignment and replacing galvanized steel service lines where discovered.

Scope 2: Lee S Dukes High Density Polyethylene (HDPE) Pipeline consists of the installation of 6,000 LF of new 3-inch x 6-inch diameter double wall containment pipe for new chlorine dioxide chemical feed system, including all appurtenances, leak detection system, electrical, testing, and final commissioning. Installation of two (2) new 2-inch diameter HDPE raw water sample lines (approximate length is 6,000 LF for each), including all appurtenances, and testing. Installation of a new raw water sample pump, casing, piping, appurtenances, electrical, and testing at the Raw Water Intake at Blythe Landing. Removal and replacement of various chemical feed lines (11/2-inch and 4-inch diameter) inside existing 8-inch and 12-inch diameter casing pipes. Installation of new fiber optic cable (approximately 6,000 LF) between the Lee S. Dukes WTP and the Raw Water Intake. Installation of new potable water line from Highway 73 to existing Compressor Building, including all appurtenances, and testing.

FY23 Water and Sewer Infrastructure – Contract 1

This contract will provide for new water and sanitary sewer main construction throughout the Charlotte, NC water service area. The majority of this contract will be used to build projects for the Street Main Extension Program.

Sugar Creek Wastewater Treatment Plant Alkalinity Storage Replacement

This project includes the removal of two high-density polyethene chemical storage tanks and mixers, the construction of a new chemical storage tank containment area, the installation of three new chemical storage tanks (two in the existing containment area and one in the new containment area), installation of a chemical mixer at each tank, installation of a new chemical metering pump in the new containment area, construction of an enclosed pump room within the containment areas, installation of new and replacement of piping, and construction of a canopy over the new containment area.

 

Fire Station #36 HVAC Renovation

The mechanical demolition work consists of removing the five (5) existing split system gas furnaces and outdoor air-conditioning condensers, and the one (1) inline exhaust fan above the men’s locker room. All existing ceiling diffusers and grilles shall be demolished and replaced inplace in new work. Existing split system controls, bipolar ionization devices, furnace terminations, and ductwork are to be kept and reused in the new work. The new mechanical work consists of installing five (5) new split system heat pumps and gas furnaces in the same place as demolished split systems, and reusing controls, bipolar ionization, existing furnace intakes/vents and reconnecting to existing gas. Outside air dampers will be adjusted to reduce outside air flow. Existing controls will need to be reworked to account for the change from cooling-only coils to heat-pump coils. A new, smaller, inline fan will be installed in place of demolished fan above men’s locker. New diffusers and grilles will be installed in-place of demolished diffusers and grilles

Briar Creek and Paw Creek Sewer Rehabilitation

This project consists of the sanitary sewer rehabilitation of approximately 13,500 linear feet of sewer outfall with cured-in-place lining. This project will extend along the Briar Creek and Paw Creek outfalls.  A 112 linear feet 24-inch diversion sewer will also be constructed under Briar Creek along with a 118 linear feet 8-inch linear feet collector sewer.

FY23 Large Diameter/Sewer Service Contract #1 (Re-bid)

This contract will incorporate the installation of water and/or sanitary sewer services at a single address, water and/or sanitary sewer service dismantlement at a single address or a water/sanitary sewer main line extension. There maybe more than one water and/or sanitary sewer service installation , water and/or sanitary sewer service dismantlement at the same address. Additionally, a single commercial site with water and/or sanitary sewer services to be installed or water and/or sanitary sewer services to be dismantled at different addresses is to be considered one project for the entire commercial site.

FY23 Small Diameter Water/Sewer Service Contract #2 (Re-bid)

This contract is for water and sanitary sewer service installations including connection to the existing public main, which extends a small diameter line to the property.  Additionally, a water meter box or sanitary sewer cleanout is included. Customers pay connection fees for the installation service, which is based on costs incurred by Charlotte Water in these contracts. The work covered by this contract will provide approximately 800 total services.

Roof Replacement and Building Envelope Repairs

The purpose of this contract is to perform roof replacement and building envelope repairs for two buildings located at 4800 and 4814 West Boulevard, Charlotte, North Carolina. Estimated term to be less than one year.

Collective Storm Drainage Improvement Project – Series S

Work performed under this contract will consist of storm water infrastructure repair and improvement projects within the city limits of Charlotte, NC.  Work will involve mobilization, earthwork, drainage structures, storm drain pipe systems, channels, working over, under, near, and around existing private utilities, asphalt paving, concrete flatwork, and landscaping and any associated work required by the Engineer. Other work may include structural foundation protection, storm water pipe lining, storm water pipe joint and structure repair, water, and sewer (relocations, installations and adjustments). Storm Water maintenance work may be located entirely within or a combination of the street right-of-way, private, residential, and commercial properties.