Central Kilborne Norland Intersection & Street Upgrade

Limits are from Woodland Dr. to just south of Havenwood Rd. / Kilborne Dr. intersection (.87 miles). The project includes a new urban greenspace named Potter Place (including public art), separated bike lanes, protected intersection improvements at Central Ave., wayfinding, storm drainage, street trees, and pedestrian medians.

Prosperity Church Road (Old Ridge to Benfield) Improvements

The project proposes to widen Prosperity Church Rd approximately 0.3 mi between Old Ridge Rd and Benfield Rd to provide curb and gutter, sidewalk, storm drainage, bicycle lanes, and on-street parking, as well as a roundabout at Prosperity Church Rd and Prosperity Ridge Rd.

6th and Church Pipe Repair

This project consists of 400 LF of existing 24” RCP along 6th St, from N Church St to N Popular St, will be rehabilitated through pipe bursting methods. Two work pits will be excavated, one at the corner of 6th & N Church St, and the other at 6th & N Popular St. The project will require road closures at 6th & N Church St and 6th & N Popular St, and 1 lane closure along 6th street. A new stormwater junction box will be installed at the corner of 6th street and N Popular St.

 

Coliseum Creek Repairs (Informal)

This project is bordered by Speer Boulevard, West Tyvola Road, and Yorkmont Road. The drainage system is open channel that was a previously stream restoration project. This project will repair one of the previously restored channel reaches.

 

On-Call General Contractor

The Facilities Division of CLT maintains portfolio buildings, including terminals, offices, fire stations, tenant occupied spaces, and equipment shops. The intent of this solicitation is to select multiple companies to provide general contractor services for various airport properties on an as needed basis. The scope of services is required to assist the airport with renovations, remodels, and maintenance of existing facilities. Expenditures for each task estimated not to exceed $30,000 but companies may be assigned multiple tasks under the contract.  The company shall provide services at various locations as needed. The city may solicit a quote for general contractor services from one or more companies prior to assigning an individual project.

Sunset Elevated Water Storage Tank

This project consists of constructing one new elevated storage tank 2 MG (million gallons in size). There will be waterline work associated to extend the mainline to the tank site. The selected firm would be asked to provide clearing and grading services in preparation of the tank installation.

Vest Water Treatment Plant to Franklin Water Treatment Plant Force Main and Lee Duke Water Treatment Plant Chem Feed Improvements

 The Project consists of two scopes of work.

Scope 1: Vest Water Treatment Plant to Franklin Water Treatment Plant Force Main consists of installing over 16,000 linear feet of 16” ductile iron piping force main for residual and backwash transfer between the Vest Water Treatment Plant and the Franklin Water Treatment Plant. Installation of all associated fittings, valves, air release valves, trenching, trenchless crossings, parallel future piping, paving, connections, corrosion control, erosion control, cleaning, testing, and all other associated pipeline work. Installation of two crossings at CSX railroad and NCDOT I-85 Interstate, consisting of parallel 16” ductile iron carrier pipe inside single casing. Reporting on material of service connections along alignment and replacing galvanized steel service lines where discovered.

Scope 2: Lee S Dukes High Density Polyethylene (HDPE) Pipeline consists of the installation of 6,000 LF of new 3-inch x 6-inch diameter double wall containment pipe for new chlorine dioxide chemical feed system, including all appurtenances, leak detection system, electrical, testing, and final commissioning. Installation of two (2) new 2-inch diameter HDPE raw water sample lines (approximate length is 6,000 LF for each), including all appurtenances, and testing. Installation of a new raw water sample pump, casing, piping, appurtenances, electrical, and testing at the Raw Water Intake at Blythe Landing. Removal and replacement of various chemical feed lines (11/2-inch and 4-inch diameter) inside existing 8-inch and 12-inch diameter casing pipes. Installation of new fiber optic cable (approximately 6,000 LF) between the Lee S. Dukes WTP and the Raw Water Intake. Installation of new potable water line from Highway 73 to existing Compressor Building, including all appurtenances, and testing.

FY23 Water and Sewer Infrastructure – Contract 1

This contract will provide for new water and sanitary sewer main construction throughout the Charlotte, NC water service area. The majority of this contract will be used to build projects for the Street Main Extension Program.