Six Mile Creek PS Improvements-Cancelled

The purpose of this project is to eliminate the long shafts between the pumps and motors. Custom motor stands will be built to position the motors over the pumps. The original two motors for this pump station will also be replaced.

Upper Taggart Creek Outfall Replacement

Project includes the construction of approximately 10,200 linear feet of 36, 30, 24, and 18 inch gravity sewer to address capacity concerns in the Upper Taggart Creek Outfall.

PS & WAS Pipelines from Irwin to McAlpine-Cancelled

Two separate lines will be needed for the solids transfer to handle the PS and WAS respectively. The PS & WAS Pipelines from Irwin Creek to McAlpine Creek Wastewater Treatment Plant will be approximately 12 miles.

Catawba River Water Pump Station Cell 4 – Pump Addition -CANCELLED

This project would add an additional pump to Cell #4 which is sized like the existing, and a capacity of 65 million gallons per day.

The Catawba River Water PS Cell 4 Pump Addition should be cancelled.  It has been pushed out in the CIP and will not be available in January 2024.  There is no updated timeline on this project.