Asset Management performed an inspection of the dual 72-inch CMP beneath N Hoskins Road in May 2024. Several holes with visible soil were observed during the inspection. Severe road settlement was also noted above the culvert. The City intends to replace 105LF of duel 72” CMP with 105LF of 11’x8” RCBC; add (2) Non-standard headwalls; add 120 LF of 54” RCP; remove 21LF 36” RCP; add (2) DCBs; Add (1) CB; replace approx. 253LF of 12” sewer; replace approx. 120LF 8” Sewer; replace (4) sewer manholes; Add/replace approx. 382LF 2’6” C&G; asphalt replacement
Lancer Dr 6818 Storm Drainage Improvement Project
Project initiated due to several holes and corrosion in the existing 16.25’x9.5’ elliptical pipe. Cracks in the headwalls were also observed. The City intends to replace 81LF 16.25’x9.5’ elliptical pipe with 81LF of 14’x9’ RCBC; add (2) Non-standard headwalls; add 213 LF of 24” RCP; replace 56LF of 15” RCP; add (3) CBs; Add (2) JBs; plug and fill approx. 220LF of 18” RCP; Add/replace approx. 600LF 2’6” C&G; channel grading; asphalt replacement.
Perth-Milton Storm Drainage Improvement Project
Proposed installation of residential access bridge, stream improvements, and storm drainage infrastructure in Perth Court area.
Euclid Avenue 1818 Storm Drainage Improvement Project
The project involves analysis of existing conditions to determine portions of the storm drainage system needing improvement, and design and construction of needed improvements. The existing storm system experienced a pipe collapse due to poor condition of the pipe. To address the request and meet level of service design standards the project will remove and replace the existing Storm Drainage Infrastructure within the project scope.
Proposed improvements include removing approximately 343 LF of 18″ storm water pipe and replace with approximately 410 LF of 24″ storm water pipe, add 2 double catch basins and associated items, and remove and replace approximately 357 LF of 8″ sewer pipe, and 3 sewer manholes.
9832 Grasmere Dr Storm Drainage Improvement Project
The scope of this project will be the installation of approximately 160 LF of concrete block retaining wall to address severe bank erosion.
Linda Lake and Oakwood Dams 2025 Rehabilitation
Proposes to rehabilitate and repair high-hazard dam discharge infrastructure, under drains, and storm drainage infrastructure at both Linda Lake and Oakwood Dams.
Gleneagles Storm Drainage Improvement Project
The Gleneagles Project is primarily focused on replacing an existing CMP culvert near 3810 Gleneagles Road. The existing culvert is 8.7’ high by 7.8’ wide and is being replaced with a 10’ wide and 7’ tall RCBC. The culvert replacement is occurring to address aging infrastructure and to improve the reliability of infrastructure for the traveling public. In support of this culvert replacement, we are dredging the downstream pond which is located on the Quail Hollow Country Club near the 15th hole. The dredging will remove sediment that has built up near the downstream end of the existing culvert and prevent sediment transport downstream which would negatively impact existing ponds and habitats. In addition, we will be adding inlets and upgrading roadside drainage on Out-Of-Bounds Drive which has significant spread in larger storm events from road drainage. The work on Out-Of-Bounds Drive will increase the safety of the traveling public using that roadway during rain events.
Bruns Academy Water Quality Enhancement Project
There is an existing wetlands system and stream adjacent to the Bruns Academy that are in need of improvements. The intent of this project is to reset an existing wetlands system to its original design and provide enhancement, where applicable. Wetland restoration efforts will include regrading, sodding and planting of vegetation, installation of a new pedestrian bridge and retaining wall. Additionally, stream improvements, such as regrading banks and adding riffles, are proposed. The proposed improvements will enhance the overall performance of the system for conveying and treating stormwater.
Hastings Princeton Storm Drainage Improvement Project
The Hastings/Princeton Storm Drainage Improvement Project will reduce street and structure flooding throughout the neighborhood. Located within a drainage area of approximately 80 acres, the project will replace aging infrastructure and provide adequate system capacity. The project area is bordered by Wellesley Avenue to the north, Hastings Drive to the south, Selwyn Avenue to the east and Jamestown Drive to the west.