Scope Statement: CFD plans to build a temporary firehouse for the newly developed River District to manage response volumes in the area. The firehouse will be located on Dixie River Road, near the future Catawba Crossing, on parcel number 14128101.
The Phase 1 facility will be (1) triple wide trailer to house the firemen and a pre-engineered building to serve as an apparatus bay to house the fire engine and emergency equipment.
This location and site selection meets the City of Charlotte Policy for Sustainable City Facilities and Charlotte Fire Department Facilities Master Plan.
This Project will install 270 LF of proposed 12′ wide multi-use-path, curb ramps, crosswalks across NC 49, Pedestrian concrete island, milling/resurfacing, storm drainage and pedestrian hybrid beacon with mast arms near the intersection of University Blvd and Mark Twain Road. This project will also install pedestrian crossings, wheelchair ramps, traffic signals milling/resurfacing and storm drainage system at the intersection of University City Blvd and Suther Rd.91347
This project will provide new sidewalk along Sardis Road North from Sardis Road to westernmost intersection of Rittenhouse Circle and Sardis Road North. Project length = 0.5 miles.
This project will include the following:
6′ Sidewalk
8′ Planting Strips
2′-6″ Curb and Gutter
Street Trees
Concrete Ped Refuge Island (between Kilcullen Dr. and Rittenhouse Circle)
Concrete Bus waiting pads
Retaining Walls
Curb Ramps
Storm Drainage
The project consists of intersection improvements at Remount Rd and West Blvd including sidewalks, curb and gutter, decorative concrete surface treatments, bus shelters with amenities, pedestrian-scale lighting, crosswalks, curb ramps, pedestrian crossing signalization, and landscaping.
This project will install a 6′ concrete sidewalk, 8′ planting strip, concrete curb ramps, Pedestrian Refuge Island, concrete driveways, 2′-6″ concrete curb and gutter, storm drainage systems, and street trees along Margaret Wallace Road from Summerfield Ridge Lane to Marshbrooke Road. The project length is 1,900 LF/0.40 miles.
This traffic signal contract will provide resources to install and maintain traffic signals and support infrastructure citywide.
This project is located on Sharon Road at Eastburn Road. The project proposes a curve realignment adding a left-turn lane from Sharon Road on to Eastburn Road and removing the superelevation.
The purpose of the CMPD Animal Care and Control, Phase 3 Expansion project is primarily to provide additional kennels for dogs and reduce the increasing rate of euthanasia. Secondly, to provide additional space for other animals and improve the efficiencies of operations for the facility. The expansion of the facility will possibly be located at 2700 Toomey Avenue and the parcel is currently 4.67 acres. This is the old location for the Animal Humane Society. We are currently in the advanced planning phase to acquire a schematic design to confirm the estimated construction cost.
The Construction delivery system will be Progressive Design Build. It is also anticipated that the city will acquire an Owner’s Advisor to assist with procurement and additional services during design and construction.
The Matheson to Craighead segment of the Cross Charlotte Trail will implement a 14-foot shared use path beginning at E 36th Street. The path will continue down Cullman Ave and board walk up into a pedestrian bridge spanning the Norfolk Southern Railroad tracks utilizing a prefabricated structure within railroad right of way. The structure will then connect to the existing trail built by Brand Properties within the Kaleido Noda apartment complex.