An extension of McCullough Drive, from it’s current terminus east
of southeast of North Tryon Street, to the disconnected terminus
southwest of W.T. Harris Blvd. It is already designed and real
estate acquired. This is necessary for splitting this project apart
from the McCullough Streetscape Project. Length = 0.272 miles
WT Harris SUP (JW Clay to N Tryon)
A 12’ wide shared-use path will be installed along WT Harris Blvd, from JW Clay Blvd to N Tryon St. This includes pedestrian ramps, storm drain services, and new pavement markings in addition to the shared-use path. Project Length = 0.33 miles.
Arrowood at Whitehall Commons Intersection
This is an intersection project which will involve installing a new traffic signal with pedestrian signals, widening some of the approaches, replacing all curb ramps, mill & overlay, and pavement markings. The traffic signal will use steel strain poles.
Sardis Road North Sidewalk
This project will provide new sidewalk along Sardis Road North from Sardis Road to westernmost intersection of Rittenhouse Circle and Sardis Road North. Project length = 0.5 miles.
This project will include the following:
6′ Sidewalk
8′ Planting Strips
2′-6″ Curb and Gutter
Street Trees
Concrete Ped Refuge Island (between Kilcullen Dr. and Rittenhouse Circle)
Concrete Bus waiting pads
Retaining Walls
Curb Ramps
Storm Drainage
7th Street Parallel Bike Routes
This project will build bike facilities in several different locations throughout the Elizabeth neighborhood to create safer conditions and improve ease of travel for cyclists and pedestrians, including approximately 2.1 miles of sharrows, modernization of two existing rectangular rapid flashing beacons, replacement of 10 wheelchair ramps, a new pedestrian crossing at Pecan Avenue and Shenandoah Avenue, implementation of new bike detection cameras, a new full traffic signal at Bascom Street and 7th Street, and a curb extension located at the intersection of Pecan Avenue and 8th Street.
Cross Charlotte Trail (XCLT)− Matheson to Craighead
The Matheson to Craighead segment of the Cross Charlotte Trail will implement a 14-foot shared use path beginning at E 36th Street. The path will continue down Cullman Ave and board walk up into a pedestrian bridge spanning the Norfolk Southern Railroad tracks utilizing a prefabricated structure within railroad right of way. The structure will then connect to the existing trail built by Brand Properties within the Kaleido Noda apartment complex.
CMAR Services – Ashley Road/Tuckaseegee Road & Freedom Drive Intersection
The project area includes the intersection area and approaches for Ashley Road/Tuckaseegee Road (State Road 1662), and Freedom Drive (NC Highway 27). Currently, the area lacks adequate pedestrian and bicycle infrastructure, limiting safe mobility and access to key destinations such as the Mecklenburg County Valerie C. Woodard Community Resource Center.
CMAR Services – Cross Charlotte Trail (XCLT) Matheson to Craighead
The Matheson to Craighead segment of the Cross Charlotte Trail will implement a 14-foot shared use path beginning at E 36th Street. The path will continue down Cullman Ave and board walk up into a pedestrian bridge spanning the Norfolk Southern Railroad tracks utilizing a prefabricated structure within railroad right of way. The structure will then connect to the existing trail built by Brand Properties within the Kaleido Noda apartment complex.
Charlotte Fire Station #2 – Addition and Renovations
The work consists of the addition and renovation of an existing fire station. The locker and restroom facilities will be renovated and expanded. Accessibility improvements are planned in various areas throughout the building and site.