Dredging of pond forebay, addition of stormwater pipe, and replacement of existing box culverts to address forebay erosion issues at the site.
Collective Storm Drainage Improvement Project Series AA
Work performed under this contract will consist of storm water infrastructure repair and improvement projects within the city limits of Charlotte, NC. Work will involve mobilization, earthwork, drainage structures, storm drain pipe systems, channels, working over, under, near, and around existing private utilities, asphalt paving, concrete flatwork, and landscaping and any associated work required by the Engineer. Other work may include structural foundation protection, storm water pipe lining, storm water pipe joint and structure repair, water and sewer (relocations, installations and adjustments). Storm Water maintenance work may be located entirely within or a combination of the street right-of-way, private, residential, and commercial properties.
Sweden Road Water Quality Enhancement Project
This project consists of the installation of Storm Water structures including pipe, curb, manholes, headwalls, and hydrodynamic separators to improve water quality at the adjacent surface water.
Storm Water Repair and Improvement FY2024-G
Work performed under this contract will consist of storm water infrastructure maintenance, repair and improvement projects within the city limits of Charlotte, NC. Work may include but is not limited to mobilization, earthwork, installation of storm drainage structures and pipes/culverts, working over, under, near, and around existing private utilities, asphalt paving, concrete flatwork, landscaping and any associated work required by the Engineer. Other work may include structural foundation protection, storm drainage structure and pipe repair and/or rehabilitation pipe lining, water and sanitary sewer (relocations, installations, and adjustments). Locations of work will vary and can be within public right of way, private property with easements or a combination of both.
Rea Road Widening (I-485 to Williams Pond Lane)
The purpose of this project is to increase capacity along Rea Road. Capacity will be increased by utilizing the right turn lane drops and median to develop an additional NB and SB through lane along Rea Road between the I-485 ramps and Williams Pond Lane. This project will also result in increased turn lane capacity and intersection improvements at Piper Station Drive and Ballantyne Commons Parkway. Pedestrian safety and mobility will be improved by providing sidewalks on both sides of Rea Road. Other specific improvements include: curb and gutter, accessible ramps, and driveways.
Firehouse # 46 Infill Station at Miranda Road
A new infill firehouse will be designed and constructed at 4032 Miranda Road to alleviate high call volumes and meet response time standards in the area. The firehouse will reflect the design of Firehouse #45, a 3-bay, 2-story firehouse programmed for approximately 14,600 square feet. The proposed facility will be located at the corner of Beatties Ford Road. Parcel #03741123 is approximately 6.54 acres. This location and site selection meets the City of Charlotte Policy for Sustainable City Facilities and Charlotte Fire Department Facilities Master Plan.
Wharton-Smith has been awarded CMAR services and is working on prequalifying subcontractors for the project.
River District Firehouse – Phase 1
Scope Statement: CFD plans to build a temporary firehouse for the newly developed River District to manage response volumes in the area. The firehouse will be located on Dixie River Road, near the future Catawba Crossing, on parcel number 14128101.
The Phase 1 facility will be (1) triple wide trailer to house the firemen and a pre-engineered building to serve as an apparatus bay to house the fire engine and emergency equipment.
This location and site selection meets the City of Charlotte Policy for Sustainable City Facilities and Charlotte Fire Department Facilities Master Plan.
North Tryon St Left Turn Lane at University City Blvd
The purpose of this project is to improve traffic flow on North Tryon Street by extending the left turn lane. This project will include lane widening, drainage and pavement markings.
Sardis Road North Sidewalk
This project will provide new sidewalk along Sardis Road North from Sardis Road to westernmost intersection of Rittenhouse Circle and Sardis Road North. Project length = 0.5 miles.
This project will include the following:
6′ Sidewalk
8′ Planting Strips
2′-6″ Curb and Gutter
Street Trees
Concrete Ped Refuge Island (between Kilcullen Dr. and Rittenhouse Circle)
Concrete Bus waiting pads
Retaining Walls
Curb Ramps
Storm Drainage