McDowell WWTP UV Disinfection Improvements

This project includes replacing all the components of the existing UV system at McDowell Wastewater Treatment PLant. This will also require temporary disinfection capabilities throughout the installation of the new UV system.

Franklin WTP 24 MOD Improvements

This project will include the installation of 39 new valves inside of the 24 MOD. The existing valves have reached their useful life. These valves have been purchased separately by Charlotte Water.

Irwin Creek WWTP UV Disinfection Improvements

This project includes replacing all the components of the existing UV system at Irwin Creek Wastewater Treatment Plant. This will also require temporary disinfection capabilities throughout the installation of the new UV system.

McDowell WWTP Headworks Improvements

This project will include the replacement of the 30″ influent pump station knife gate valves at the discharge header with new plug valves. Additional piping that is failing will need to be replaced along with valve actuators and electrical components. Replacement of malfunctioning gates will also need to be replaced.

Lee Dukes Alum Bulk Storage Replacement

This construction contract is for the replacement of the Alum Bulk Storage tanks at the Lee Dukes Water Treatment Plant. The project will also include replacement of the existing piping between the day tanks and the bulk storage and the piping between the bulk storage tank to the delivery fill location.

Irwin Creek WWTP Stormwater Improvements Project

This construction contract will replace existing diesel pumps with electric submersible pumps. This will be done at three locations at the existing stormwater outfall locations. The project will also include installation of permanent discharge piping at stormwater outfall 1. This will require electrical duct bank along with wiring and all necessary components to power the pumps.

Lee Dukes Chemical Feed Piping Replacement

This construction contract will be for the replacement of the chemical feed piping at the Lee Dukes Water Treatment Plant. The piping replacement will pertain primarily to the chlorine feed system and the alum feeds.

Ashe Plantation Lift Station

This contract will be for the construction of a 250,000 gallon-per-day duplex lift station and demolition of the existing wastewater treatment package plant. Included will be the construction of an emergency containment basin, upsizing of an existing gravity sewer, installation of a portion of an 8″ force main, new wet well. Owner plans to procure pumps and standby generator for the project.

Lift Station Improvements Phase III

This construction contract is for various improvements and rehabilitation needs at six of our lift station sites. General improvements will include reck-mounted control cabinets at grade level, new submersible pressure transducers, new wet well level floats, installation of a magnetic flow meter in a precast vault with a bypass on the existing force main.