Roof Replacement at the Blumenthal Performing Arts Center
This work includes the provision of labor, material, equipment, supervision and administration to includes:
1. Roof Areas C1‐C3, D, E1‐E3, F1‐F3 and G:
a. Remove and dispose of base flashings, walkway pads and sheet metal.
b. Prepare two‐ply modified bitumen roof membrane to receive recovering roof system.
c. Provide a cold adhesive applied two‐ply modified bitumen roof membrane along with
flashings and accessories.
d. Replace sheet metal flashings and trim.
e. Provide a complete, watertight, 20‐year extension to existing roof system warranty.
2. Exterior Wall Restoration:
a. Replace elastomeric joint sealants at control joints and expansion joints at elevation walls
above roof level from through wall flashing up 6 feet.
b. Replace through wall flashings at masonry elevation wall above roof level.
c. Replace through wall flashings at window/door heads.