The Project consists of an undetermined number of individual projects consisting of water and/or sewer extensions,
water and/or sewer replacements, low-pressure sanitary sewer, water distribution system reliability
improvement projects, and/or sanitary sewer capacity assurance projects, which will be assigned by the
Project Engineer.
FY26 Water and Sewer Infrastructure Construction – Contract 1
The Project consists of an undetermined number of individual projects consisting of water and/or sewer extensions,
water and/or sewer replacements, low-pressure sanitary sewer, water distribution system reliability
improvement projects, and/or sanitary sewer capacity assurance projects, which will be assigned by the
Project Engineer.
Thermal Road Culverts Storm Drainage Improvement Project
This project will replace to existing culverts that have reached the end of their serviceable lifespan at two locations along Thermal Road with new reinforced concrete pipe culverts.
Ashe Plantation Lift Station
The Ashe Plantation Lift Station project involves the design, bidding, and construction of a new lift station utilizing the existing wet well built during Phase I of the Ashe Plantation Wastewater Treatment Plant. The proposed system is a duplex lift station with a capacity of 320 gallons per minute, which will connect to an 8-inch forcemain. This new infrastructure will convey wastewater to the Goose Creek basin. As part of the project, the existing package treatment plant will be decommissioned.
McDowell Creek Wastewater Treatment Plant Primary Clarifier and Influent Pumping Station Rehab
This project includes the demolition and disposal of the existing Primary Clarifier No. 5 (PC No. 5) mechanism and associated components, followed by the installation of a new Owner-procured clarifier mechanism. Additional work at PC No. 5 includes structural repairs, replacement of exposed piping and valves, modifications to existing chemical feed dosing points, and upgrades to slide and sluice gate components. At the Influent Pump Station (IPS), the project involves replacing existing grit piping and stainless steel air piping. The IPS scope also includes the replacement of slide gate seals, actuators, and stems to ensure continued operational reliability.
McAlpine Creek WRRF Digesters Rehabilitation
The McAlpine Digesters Rehabilitation project focuses on restoring key components of the biosolids treatment facilities. This includes structural repairs and a new cover for the first digested sludge storage tank, along with installation of new sludge pumps, valves, and piping. The project also replaces an outdated programmable logic controller system and adds a new sludge line to separate gravity-fed and pumped flows. Additional improvements include a new dewatering well system for draining the storage tanks and structural evaluation and repairs to the second digested sludge storage tank.
FY26 Sanitary Sewer Rehabilitation
The Project consists of constructing rehabilitation of manholes, repair of sewer system defects and service laterals, installing new sewers and manholes to replace existing sewers and manholes, installation of cured-in-place pipe lining, pipe bursting, other miscellaneous manhole rehabilitation work, and all preparatory work such as sewer cleaning and television inspection.
CTC Fare Zone Striping
The Charlotte Area Transit System (CATS) anticipates contracting out the following work:
The CTC Fare Zone Striping project is a part off safety and security improvements at the Charlotte Transportation Center that will include the installation of the following approximate quantities of heated-in-place thermoplastic markings:
-950 linear feet of customized 2′-wide blue striping labeled with “FARE ZONE”;
-470 linear feet of pedestrian crosswalk (8 separate crosswalks); and
-920 linear feet of safety yellow striping for 23 bus bays.
Other additional work includes the installation of 31 yellow truncated domes, removal of existing crosswalk striping, and providing 121 linear feet of additional blue “FARE ZONE” striping to be turned over to CATS.
Heat-in-place thermoplastic will be installed per NCDOT specifications. The crosswalk and truncated dome will match the City of Charlotte Land Development Standards.
PSR # 1917
Firehouse 44
Firehouse 44 will be an integral asset to support Charlotte Fire Department’s efficient response to emergencies in the community; providing a location within the newly developed River District community and expanding their response area in this newly incorporated region of Charlotte. This 14,600 SF, two-story, 3-bay facility will be the first mass timber firehouse in the Southeast US and will meet Living Future’s (LF) Zero Carbon certification for total project embodied carbon. The project will comply with Charlotte’s Sustainable Facilities Policy and fully support the sophisticated and time-sensitive operations of the Fire Department.