FY26 Sanitary Sewer Rehabilitation

The Project consists of constructing rehabilitation of manholes, repair of sewer system defects and service laterals, installing new sewers and manholes to replace existing sewers and manholes, installation of cured-in-place pipe lining, pipe bursting, other miscellaneous manhole rehabilitation work, and all preparatory work such as sewer cleaning and television inspection.

CTC Fare Zone Striping

The Charlotte Area Transit System (CATS) anticipates contracting out the following work:

The CTC Fare Zone Striping project is a part off safety and security improvements at the Charlotte Transportation Center that will include the installation of the following approximate quantities of heated-in-place thermoplastic markings:
-950 linear feet of customized 2′-wide blue striping labeled with “FARE ZONE”;
-470 linear feet of pedestrian crosswalk (8 separate crosswalks); and
-920 linear feet of safety yellow striping for 23 bus bays.
Other additional work includes the installation of 31 yellow truncated domes, removal of existing crosswalk striping, and providing 121 linear feet of additional blue “FARE ZONE” striping to be turned over to CATS.

Heat-in-place thermoplastic will be installed per NCDOT specifications. The crosswalk and truncated dome will match the City of Charlotte Land Development Standards.

PSR # 1917

Firehouse 44

Firehouse 44 will be an integral asset to support Charlotte Fire Department’s efficient response to emergencies in the community; providing a location within the newly developed River District community and expanding their response area in this newly incorporated region of Charlotte. This 14,600 SF, two-story, 3-bay facility will be the first mass timber firehouse in the Southeast US and will meet Living Future’s (LF) Zero Carbon certification for total project embodied carbon. The project will comply with Charlotte’s Sustainable Facilities Policy and fully support the sophisticated and time-sensitive operations of the Fire Department.

Safe Streets for All (SS4A) – Phase 1

This project includes safety improvements at 8 sites, focusing on low-cost, high-impact measures such as pedestrian crossings, accessible pedestrian signals (APS), leading pedestrian intervals (LPIs), and priority projects from a Safe Routes to School study.

CMGC- ADA Implementation – Ph 2 – Highrise & Parking Deck

This project will address the non-conforming, physical ADA barriers to the greatest extent feasible and where applicable under code provisions. Phase 2 includes the Charlotte-Mecklenburg Government Center and adjacent Parking Garage.  Scope areas include Exterior Plaza, Entrance Lobby, 2nd Floor Mezzanine and the 15-story Highrise. Specific scope includes, but is not limited to, Partitions, Doors and Door Hardware, Ramps, Millwork, Restrooms, Controlled Access, Obstructions, Plaza Deck and Accessible Routes. The project delivery method is Construction Manager at Risk (CMAR).  The CMAR will commence with CBI outreach ~3rd qtr 2025 and trade partner pre-qualification ~4th qtr 2025.

Bryant Farms Phase 2 (Design-Build)

This purpose of the Bryant Farms Road Extension, Phase II project is to continue the street connection of Bryant Farms Road between Rea Road and Ardrey Kell Road. The design is anticipated to include a two-lane road with turn lanes, shared-use path on both sides of the road, and improvements at the intersections of Bryant Farms Road with Rea Road, Tom Short Road, and Ardrey Kell Road. The project will also build a crossing over Flat Branch stream and will run adjacent to the Flat Branch Nature Preserve for a portion of the project.

Fixed-Based Operations North Basin Retrofit

The FBO North Basin Retrofit project will be for the purpose of retrofitting an existing dry stormwater detention basin situated along Airport Drive. Work under this project will include relocating a section of Security Identification Display Area (SIDA) fence, constructing a new riser system, repairing the outfall pipe beneath Airport Drive, and completing some minor grading within the basin itself. This work is expected to have a duration of approximately 60 days. Due to security fence relocation, the contractor may be required to obtain a SIDA badge.

CMPD HQ THIRD FLOOR 911 ALTERATIONS

Alterations to the Charlotte-Mecklenburg Police Headquarters include but are not limited to: demolition to the interior space, new wall, new ceilings, new floor and wall finishes, and alterations plumbing, HVAC, fire protection, and electrical systems.