Home » Opportunities » PS & WAS Pipelines from Irwin to McAlpine-Cancelled
Charlotte Water / Construction
PS & WAS Pipelines from Irwin to McAlpine-Cancelled
Details
Posting Number
03
2020-Q1(Jan-Mar)-CW-1237
Anticipated Posting Date2020-03-31
Commodity Code(s):91200, 92500
Two separate lines will be needed for the solids transfer to handle the PS and WAS respectively. The PS & WAS Pipelines from Irwin Creek to McAlpine Creek Wastewater Treatment Plant will be approximately 12 miles.
Requirements
Last Updated: 11/15/20
Insurance Requirements+
Automobile-For automobile operations liability
General Liability-For bodily injury or property damage, arising from products, premises, completed work, personal & advertising injury
Pollution Legal Liability-For transit of pollutants (on auto liability) or contamination of work site, and off-site
Workers Compensation-For lost wages and medical expenses of injured workers
Bonding Requirements+
Bid Bond-City required Bond to ensure that vendors do not retract bids from the time they submit a bit until the contract has been executed.
Payment Bond-City required Bond to ensure that subcontractors and/or suppliers are paid for any work performed.
Performance Bond-City required Bond to ensure satisfactory completion of a project by the vendor.
Subcontracting Opportunities+
Subcontracting Opportunities
Goal will be established once design is complete
Estimated Total Value+
$1,000,000 -4,999,999
Contract Term+
Not to Exceed
Follow This Opportunity!