Charlotte Area Transit System / Construction
CATS MOW Tremont Grade Crossing Gate Mast Relocation FY24 Shutdown CANCELLED
Details
Posting Number 08 2023-Q3(Jul-Sep)-CATS-10604
Anticipated Posting Date 2023-08-14
Commodity Code(s): 55006, 91344, 94065
Contractor shall furnish the necessary equipment, traffic control and labor to remove the existing west bound traffic gate and install a new gate per the approved Plans. The Owner (CATS) shall provide the existing cable, gate foundation and new crossing gate, with all appurtenances, to be installed.
Contractor shall:
A. Contractor shall submit a schedule and detailed workplan for approval prior to the start of work.
B. Contractor shall develop, and submit for approval, test procedures and test forms for the new gate and crossing prior to executing field work.
C. Set up approved traffic control to protect the crossing during the Work both vehicle traffic and pedestrian traffic..
D. Remove the existing gate and deliver it to the North Yard Maintenance Facility or other CATS property as directed.
E. Remove all, or a sufficient amount, of the gates’ foundation so as to replace the soil and sidewalk.
F. Contractor shall demolish the sidewalk and excavate for a new gate foundation per approved Plans. Existing conduit shall be intercepted and rerouted into the new foundation. Contractor shall provide the necessary conduit, sweeps, supports, couplings and glue. Existing cable shall be un-landed, tested and terminated for the new gate.
G. Contractor shall remove and install new ADA compliant Truncated Dome.
H. Contractor shall set the new foundation and gate, provided by the Owner, and adjust gate arm length, counterweights, arm lights and light directions per the approved Plans and MUTCD requirements.
I. Contractor shall test the new gate and crossing operation.
J. Contractor shall submit test results for review and approval.